Lift scheduling organization : Lift Concept for Lemminkainen
Mingalimov, Iurii (2015)
Mingalimov, Iurii
Saimaan ammattikorkeakoulu
2015
All rights reserved
Julkaisun pysyvä osoite on
https://urn.fi/URN:NBN:fi:amk-201505229593
https://urn.fi/URN:NBN:fi:amk-201505229593
Tiivistelmä
The purpose of the work was to make a simple schedule for the main contractors and clients to check and control workflow connected with lifts. It gathers works with electricity, construction, engineering networks, installing equipment and commissioning works.
The schedule was carried out during working on the building site Aino in Saint Petersburg in Lemminkӓinen. The duration of work was 5 months.
The lift concept in Lemminkӓinen is very well controlled in comparison with other building companies in Saint-Petersburg. Lemminkӓinen provide KONE lifts prepared shafts as soon as possible. It always stays in touch with them and assures working conditions.
On the other hand, Lemminkӓinen is overthinking the safety on the site. This is a European way of working, but it is hard to cooperate with Russians in such a way.
It is believed that KONE was not the best option for a company installing and maintaining lifts. Anyway, because of the agreement between KONE and Lemminkӓinen, KONE was chosen to be the lift contractor.
As a result of the work the schedule was realised in Microsoft Project Software. It is simple to use. The schedule allows to change dates, name and quantity of works but shows the main duration and order of workflow.
The schedule was carried out during working on the building site Aino in Saint Petersburg in Lemminkӓinen. The duration of work was 5 months.
The lift concept in Lemminkӓinen is very well controlled in comparison with other building companies in Saint-Petersburg. Lemminkӓinen provide KONE lifts prepared shafts as soon as possible. It always stays in touch with them and assures working conditions.
On the other hand, Lemminkӓinen is overthinking the safety on the site. This is a European way of working, but it is hard to cooperate with Russians in such a way.
It is believed that KONE was not the best option for a company installing and maintaining lifts. Anyway, because of the agreement between KONE and Lemminkӓinen, KONE was chosen to be the lift contractor.
As a result of the work the schedule was realised in Microsoft Project Software. It is simple to use. The schedule allows to change dates, name and quantity of works but shows the main duration and order of workflow.