Optimising a Production Planning System : Case: Update for the Production Scheduling Software at Mölnlycke Health Care Mikkeli factory
Heikkinen, Toni (2019)
Heikkinen, Toni
2019
All rights reserved. This publication is copyrighted. You may download, display and print it for Your own personal use. Commercial use is prohibited.
Julkaisun pysyvä osoite on
https://urn.fi/URN:NBN:fi:amk-2019062817582
https://urn.fi/URN:NBN:fi:amk-2019062817582
Tiivistelmä
This thesis was commissioned by the production planning team at the Mikkeli factory of Mölnlycke Health care Oy. As a part of actions directed towards increasing the efficiency of the production planning process, the production planning team has been going through a process to update the software version of the production scheduling system in use at the factory, Infor Advanced Scheduling.
The purpose of this thesis was to optimise the production planning process at the factory by implementing the new software update together with the production planning team, making user side customisation to the updated software and finally constructing a user guide to support the usage of the software.
This thesis consists of two main objectives; first being the implementation of the new software update to the scheduling system, and the second part including the creation of a comprehensive user guide for the software.
The thesis was performed as a case study, following the progress of the software update project. The outcome of this thesis was helping the production planning team to have the production scheduling software up to date, and a user guide for operating the software.
The purpose of this thesis was to optimise the production planning process at the factory by implementing the new software update together with the production planning team, making user side customisation to the updated software and finally constructing a user guide to support the usage of the software.
This thesis consists of two main objectives; first being the implementation of the new software update to the scheduling system, and the second part including the creation of a comprehensive user guide for the software.
The thesis was performed as a case study, following the progress of the software update project. The outcome of this thesis was helping the production planning team to have the production scheduling software up to date, and a user guide for operating the software.